Slight weather delay- But quickly back at it!

Hi there!

Our home sweet home sign is still hanging strong!! Looks beautiful up here with all the snow.

We’ve had a slight delay these past few week in building due to a couple reasons. 1.) It’s been bitterly cold and we’ve gotten some snow days. 2.) We also had a delay in our lumber order. Since our floor plans on our main floor are so open, we needed custom fabricated trusses. (Very complicated roof… sorry boys!)

So the plan is… next week the steal frames and lumber will be delivered on site and our builder should start framing. The crane is already on site and ready to rock and roll. If all is well with the weather then it should take about 2 weeks. From there on out I believe we’ll be in the fast lane again.

XOXO

Hopefully to be continued very soon.

 

1-23-18

Dan was on site yesterday to meet and greet the framer! 🙂 Here are some photo’s he took of the crane, lumber and steal frames!! Everyday this week they will be dropping off more loads of lumber. SO SO EXCITING!

 

 